Project

Sytner – Knutsford

Start Date – August 06
Completion Date
– January 08
Duration
– 28 weeks
Project Value
– £300k

Design & Construction

The design and construction of a New Car Dealership with a service and repair workshop. The brown field site development included the remediation of a former paper mill site and included the construction of a new signal junction and estate roadway.

Following an initial infrastructure works programme of 14 weeks the dealership was constructed in a 28 weeks period and was handed over in December 2007 for opening in January 2008.

Key Feature

  • 7100m² site development – 660m² showrooms – 750m² 10 bay workshop
  • Two storey office and welfare accommodation
  • Wet and dry valeting facility
  • Distinctive features, gas fired VRV system